Here's a PMP Sample Question:
A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned. The SME asks the project manager to write, document, and include it in the lessons learned register.
What should the project manager do?
A. Request the SME to wait until the project closure phase.
B. Assign the documenting task to a project team member.
C. Ask the SME to document and capture the occurrence.
D. Take ownership of documenting this information.
I would like to know the correct answer to this question. What do you think is the correct answer, and why?