Friends, Below question on the free 200 questions has disputed answer. Its saying correct answer-1 and in explanation its answer 4 (which also i selected) Give your opinions Templates and forms which are available in the organization and are part of organization's ________ project plan development. Assumptions 2. Constraints 3. Software 4. Methodology Correct Answer is : 1
A is the correct answer. Templates and forms which are available in the organization are reusable components. Any resource that can be reused as a useful tool is part of the total methodology of project planning.