You are the project manager of a $400 million construction project. You, along with your team, have identified and documented the specific actions to be performed to produce the project deliverables. What would be your immediate next action be?
- Develop Schedule
- Collect Requirements
- Sequence Activities
- Select Sellers
Please provide your answer with justification. Justifying your answer with explanation helps you to remember the concept and also help others to understand. Thanks.