Sample question for PMP and CAPM certification.
Q. Procurement closure is done (choose the correct statement):
A. at the end of each project phase
B. before closing the project
C. after project closure
D. as part of the Close Project or Phase process
Post your answer below. Correct answer will be posted after receiving at least one response.